2012 Home Renovations – Part 28 – Screening of Lanai Done

Another incremental day. I’m pleased to say that you can’t really tell that the screening has all been installed 🙂 You *can* see the chair rails and the doors are now all fully operational. This first shot below is still waiting for the Lexan covering for the roof. This small part will not be screened … Continue reading 2012 Home Renovations – Part 28 – Screening of Lanai Done

2012 Home Renovations – Part 27 – Framework for Lanai is largely done

Things have been a bit busy around here lately so I’m combing the beginning and end of the day pictures this time. Yesterday they DC Enclosures guys were here and they erected the bulk of the skeleton of the new lanai Shortly after the above pictures were taken I got together with all the major … Continue reading 2012 Home Renovations – Part 27 – Framework for Lanai is largely done

2012 Home Renovations – Part 26 – Lanai parts have arrived

A bit earlier than expected (almost always a good thing in construction) was this trailer load of pieces that will eventually make up our lanai. There was a fair amount of relatively invisible work done installing the anchors around the deck and on the retaining wall. The most visible piece is the large support that … Continue reading 2012 Home Renovations – Part 26 – Lanai parts have arrived

2012 Home Renovations – Part 25 – Rock Face completed

It was hit or miss today, the original forecast for today had been 10% POP but, as can be attested to by my rained out bike ride, mother nature does not watch the weather reports. So some workmen showed up today, milled around a bit and then left. Some of the other guys came by … Continue reading 2012 Home Renovations – Part 25 – Rock Face completed

2012 Home Renovations – Part 24 – Rock Face on retaining walls has begun

Michelle was concerned about the colors of the stones that arrived from Daco Stone. The sample board we were using to drive the decision was only about 15″ x 19″ of stone and, while it largely represented what we actually received, the darkest stones were represented as no more than a couple of inch high sliver … Continue reading 2012 Home Renovations – Part 24 – Rock Face on retaining walls has begun

2012 Home Renovations – Part 23 – Columns continue and Rock Face Stones have arrived

I submitted a couple more checks that bring this project to about $115,000 so far.  The original cost was expected to be in about the $140,000 range. We’ll see. Workers were at my place all day today but what was accomplished does not jump out at you. There was progress on the columns but there … Continue reading 2012 Home Renovations – Part 23 – Columns continue and Rock Face Stones have arrived

2012 Home Renovations – Part 22 – New Columns and Tile Sawing

As expected, things came to pretty much a crawl while decisions regarding rock faces and colors were being made. Three days ago new columns were installed to replace the multitude of makeshift supports The next day they came and finished sawing the existing tiles so they were even. They had originally been cut and notched … Continue reading 2012 Home Renovations – Part 22 – New Columns and Tile Sawing

Internet Speed – Are you getting what you pay for?

This past weekend I had a glitch in my Comcast internet service. On Saturday afternoon my internet connection simply died. It was pretty obvious to me that the issue was between my house and Comcast but they assured me there were no issues and that they’d send someone around to look at it… on Monday… … Continue reading Internet Speed – Are you getting what you pay for?

2012 Home Renovations – Part 21 – The Boulders are installed

With the exception of a couple of half cap stones, the modular retaining wall is complete. Once the rock face in the back is complete (and possibly the Lanai too) we’ll move forward with pulling out the remainder of the driveway and pouring a new one. We just want to have all the heavy stuff … Continue reading 2012 Home Renovations – Part 21 – The Boulders are installed

2012 Home Renovations – Part 20 – Modular Retaining wall continues

We are in that phase of the project where the work done is more incremental than it was originally. Below we see that work continues on the modular block retaining wall And initial fill behind the wall that will allow widening of the driveway also continues The dirt pile continues to shrink. We’ve had several … Continue reading 2012 Home Renovations – Part 20 – Modular Retaining wall continues